Residence Elevator Shaft Goes Up
August 23, 2007 - The most visible change on the site of the new campus is the block work for the residence elevator shaft. More of the vertical steel for the library is also in place. Crews are stripping the forms off the perimeter foundation walls of the academic centre. This perimeter foundation wall is now complete. The steel rebar for the gymnasium/performing arts centre is on site in preparation for the forming of the footings and foundation. Ambrose Circle, the thoroughfare that connects the campus buildings and encloses the campus commons, is serviced, graded and packed.