Campus Transition Schedule | Ambrose University College

Campus Transition Schedule

Campus Transition Schedule

news

June 12, 2008

Occupation of the New Campus

With the move now imminent from the downtown campus to the new campus on Calgary's West side, so is the reality of deadlines. Occupancy of the library building will begin in early July with the library collection on the main level and academic administration and faculty offices on the second level. Ambrose has sold some of its current library shelving and other items to Rocky Mountain College and Alberta Bible College to make way for the new compact shelving currently being installed.

The student residence is partially completed and somewhat behind schedule. The downtown residence was closed down April 30 and the furniture is being stored in containers at the new campus until it is moved into the new residence. Early in June armoires (dresser/closet) arrived and were moved into the residence. Lounge furniture, refrigerators and other items will be added over the summer.

The music area is scheduled for completion by July 15. The music equipment and offices will be moved as soon as the library and faculty office move is completed.

The 1st floor of the academic centre, including classrooms, food services and food court, is scheduled to be ready for set up about July 21. Business and administration offices will be moved July 31 and ready for customers August 5 at 8 AM pending receipt of the Occupancy Permit.

The 2nd floor of the academic centre is scheduled to be completed early in August. Areas included are the biology lab and offices, Student Services, Senior Administration, most classrooms and the computer commons.

Web, Email and Phone Access

Web access, computer access and phone access will be down from July 30 - August 4, 2008 in order to give Ambrose IT personnel time to move the servers and other equipment to the new campus. IT will work diligently to have everything up and functioning for August 5, including individual computer connections and phones. Priority will be given to reception, enrolment, registrar, and finance in order to resume service to the public as soon as possible.

Commercial Joint Venture

We are waiting the release of the development permit for the Commercial Joint Venture and anticipate work beginning on the project this fall with Elan as the contractor.

Cell Tower

A cell tower contract will be signed shortly for a tower at the back of our campus site. This will be a revenue source for Ambrose.

Key Dates for the Transition

June 30 Faculty offices are packed for moving

July 9 Student Link scheduled for completion and move-in

July 15 Administration /Support Staff offices are packed for moving

July 15 Music Centre move-in pending completion of facility

July 16-30 Library is unpacked

July 31 Gymnasium move-in pending completion of the floor

August 1-5 Website, Phone Services, Servers are operational on new campus

August 5 Faculty and Staff offices ready for unpacking

August 25 President's Day

September 6 Student Leaders arrive on campus

September 10 Returning Students arrive

September 11 New Student Orientation

September 15 First day of classes

Contact: Velma Warnock